Operations
Content Image

Westwood Project, Canada

Recent Developments & Outlook

Recent Developments

as at September 30, 2011

Construction

The overall plan remains on track for an early 2013 commercial start. The Westwood project expenditures, excluding exploration, in the third quarter of 2011 totaled $30.6 million (before tax credits) (first nine months of 2011 - $88.4 million) with significant infrastructure preparation and construction, including the completion of a number of hoist elements, the fire detection system with the new pump house, the waste silo foundation, and the beginning of the ground support of the six-metre diameter ventilation shaft.  During the third quarter of 2011, shaft sinking reached 1,400 metres, with the installation of a spill pocket and the safety bulkhead under the 104-0 level, and underground development work including 2,200 metres of lateral and vertical excavation achieved (first nine months of 2011 - 6,566 metres).

Exploration

Over 15,000 metres of diamond drilling was completed during the third quarter 2011 as part of the 82,000-metre 2011 underground drill program.  The costs in the third quarter were $2.2 million (before tax credits) (first nine months of 2011 - $7.6 million).  The program is designed to provide additional inferred resources and upgrade existing mineral resources to measured and indicated categories in tandem with the on-going underground development and construction of the surface installations.  As part of the development work, the exploration ramp and underground drifts were extended by 1,891 metres during the third quarter to provide better underground access for definition drilling in the upper parts of the deposit.  Better access will also improve drill positioning to target extensions to the known mineralized lenses at depth.

Four underground drills, working on expansion drilling below the 132 level, drilled over 7,100 metres during the third quarter of 2011.  In addition, five drills focused on in-fill and delineation work, drilled nearly 7,700 metres during the third quarter of 2011.  The Company is pleased with the progress year-to-date, projected expansions to the inferred resources, and the increased confidence in the reserves and resources.


2011 Outlook

    Evaluation activities planned in 2011 for a total of $125.0 million are as follows:

    • complete construction of the surface waste silo to allow ore development by the end of 2011,
    • achieve shaft sinking plan (1,560 metres by end of 2011),
    • complete the six-metre ventilation raise boring,
    • ground support to the six-metre ventilation raise boring,
    • infill and step-out drilling for resource development (82,000 metres), and
    • total vertical and horizontal development of nearly 9,500 metres.